Water Main Replacement Project Reaches 17 Percent Completion
Old cast iron water mains removed from beneath 2nd Street sit alongside an active construction zone as crews continue work on Wessington Springs' water main replacement project. (KRISTI HINE / TRUE DAKOTAN)
Construction continues to move forward on Wessington Springs' water main replacement project, with crews completing several key portions of the work and remaining on schedule for a July completion.
According to project engineer SPN, Hulstein Excavating has submitted a payment application representing approximately 17 percent of the overall project.
Since work began in May, crews have completed the w…