2nd Street Surface Installed After Years of Delays
2nd Street Surface Installed After Years of Delays
The Road Guys apply the long-awaited Otta Seal surface to 2nd Street in Wessington Springs on Tuesday, June 16. The work marks a major milestone in a project that was awarded in 2023, delayed multiple times and ultimately required the City of Wessington Springs to call the contractor's bond before work resumed this spring. Remaining paving at several intersections will be completed after the city's separate water main replacement project is finished.
After years of delays, detours and frustration, the long-awaited 2nd Street reconstruction project in Wessington Springs reached a major milestone Tuesday, June 16, as crews applied the project’s Otta Seal driving surface.The work was completed by The Road Guys, subcontracted by H&W Contracting, and represents the final major phase of a project that was originally bid in 2023 and i...